Work will begin May 16 on a $2.7 million Michigan Department of Transportation (MDOT) investment to resurface the roadway and replace a culvert onĀ M-183 in Delta County.
The project includes 2.1 miles of asphalt resurfacing, guardrail replacement, and pavement markings from the M-183/US-2 intersection south to the culvert location.
The project is scheduled to begin on Monday, May 16, 2022, and wrap up by Friday, Sept. 16, 2022
One alternating lane will be open at the culvert during work using a temporary traffic signal. Later in the summer, motorists can expect intermittent lane closures using traffic regulators during the resurfacing portion of the project. An 11-foot width restriction will be in place at the culvert.
Based on economic modeling, this investment is expected to directly and indirectly support 34 jobs.
This work will extend the lifespan of the roadway by replacing an aging culvert and will result in a smoother driving surface and increased safety for motorists.