Storm sewer work will resume Monday on the I-75 BS project in Sault Ste. Marie. Work was suspended for the season in November.
The Michigan Department of Transportation (MDOT) and the City of Sault Ste. Marie are investing $11.2 million to reconstruct 2.2 miles of roadway and construct a roundabout combining the intersections of Three Mile Road/Mackinac Trail and I-75 BS/Mackinac Trail in Sault Ste. Marie. The project began in May 2018 and is expected to be completed in spring 2020.
Project map: https://bit.ly/2KRDy7E
The current traffic configuration will be maintained, and the roundabout will continue to be open to one lane of traffic during this project phase.
This project is expected to improve safety and traffic flow in this area. Learn more about the safety benefits of roundabouts at www.Michigan.gov/Roundabout.