The Michigan Department of Transportation (MDOT) will be investingĀ $3.7 million to rebuildĀ US-41/M-28 from the Front Street roundabout to Furnace Street in the city of Marquette, Marquette County.
Work includes 0.6 miles of asphalt rebuilding; cold milling and asphalt surfacing of the roundabout; watermain, storm sewer and drainage repairs and improvements; traffic signal work; signs; and pavement markings.
The project is scheduled to start on Monday, May 16, 2022 and end by Wednesday, October 26, 2022.
One lane will be open in each direction with a center left-turn lane during the project. Temporary short-term detours will be needed during roundabout resurfacing. Some side road closures and local street detours will be needed for work at intersections.
Based on economic modeling, this investment is expected to directly and indirectly support 47 jobs.
This project will improve safety and ride quality for motorists and extend the life of the roadway.